State Library Board Delays Release Of Funds For Jones Expansion Project Due to “Financial Capacity” Uncertainty

2

Photo: flckr.com. Creative Commons

At the meeting of the Amherst Finance Committee on September 13, the committee was informed that the next payment from the Massachusetts Board of Library Commissioners (MBLC) to the Town will be delayed. The MBLC sent a letter (see below) explaining their decision to delay the $2.7 million expected mid 2023 until after a contract has been signed with a general contractor and a building permit has been issued. Those milestones are now projected out to late 2023 or early 2024. This will prompt a new cash flow analysis by the Town to determine how to cover costs in the meantime.

In strong wording, James Lonergan, Director of the MBLC, describes the multiple accommodations the commission has already made for the Jones Library Project and implies that further accommodations should not be expected. 

According to MBLC Library Building Specialist Andrea Bono-Bunker and outlined in the contract the town signed, “the Board will not be held responsible for meeting any increased costs or increasing the amount of the grant award beyond the provisional award”.

Owner’s Project Manager Craig DiCarlo has also stated that the MBLC had communicated that further reductions in the size of the building will not be accepted.

One argument put forth for continuing with this project in the face of skyrocketing cost estimates that exceed available funding by between $10 and 17 million, cites the possibility of intervention by state and regional representatives to either increase the grant or allow other changes to the existing contract. 

These recent communications from the MBLC are at odds with that hope. Lonegran concludes, “We (MBLC) have been as flexible as possible with your project to assist the Town in its fiduciary duty to its taxpayers. The same flexibility is warranted for the fiduciary responsibility our agency has to the Commonwealth’s taxpayers”

The Letter from the MBLC follows.

Spread the love

2 thoughts on “State Library Board Delays Release Of Funds For Jones Expansion Project Due to “Financial Capacity” Uncertainty

  1. Thank you , Maria, for reporting on this significant development. I think it fair to read the MBLC’s letter as a vote of diminished — or even no — confidence in the ability of the Jones Library Trustees and the Town to make this demolition/expansion project happen.

    Essentially, the MBLC will not pay the second 20% of its construction grant amount until Library and Town have met the legal criteria for disbursement of the third 20%. For the regulatory-curious, this is at 605 CMR 6.09, “Grant Disbursements,” subsections (1)(b) 2, 3.

    This protects the MBLC from disbursing the grant’s second $2.7 million, which the Town might later have to return (plus interest) for breach of contract. Of course, in case of breach, for instance, by still failing to comply with the Massachusetts Historic Preservation Law, the Town must return the first $2.7 million that it has already received, plus interest.

    The MBLC has a particular incentive for protecting its grant monies here. This is because grant amounts returned for breach of contract, and their accrued interest, do NOT go back to the MBLC. Instead, they are deposited in the Massachusetts General Fund, commingled with tax and other state revenues. So the MBLC cannot redirect such amounts to benefit other libraries.

    The MBLC’s letter might as well be handwritten on the Town Room’s wall. Town Council would do well to cancel this project accordingly.

Leave a Reply

The Amherst Indy welcomes your comment on this article. Comments must be signed with your real, full name & contact information; and must be factual and civil. See the Indy comment policy for more information.

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.