Jones Library Building Project Financial Status, November 2026: More Than $7 Million Still Owed to Town
Photo: Shutterstock
Since the last update in October 2026, the Jones Library Trustees reported making an $850,000 payment to the town toward the library’s share of the building project ($13,822,518).
The following graph shows the amounts paid and owed to the town. This information will be updated and posted regularly in the Indy.

Since August 2026, the Capital Campaign has received approximately $150,000 in new cash gifts and $760,000 in pledge payments (nearly $2 million of pledges remain unpaid).