Jones Trustees Pause Friends Pact as Fundraising Worries Loom

0
Jones Trustees Pause Friends Pact as Fundraising Worries Loom

At its November 12 meeting, the Jones Library Board of Trustees heard President Austin Sarat ask to delay a proposed agreement with the Friends of the Jones Library, while he raised a harder question: how quickly could new fundraising refill an endowment that may be tapped more heavily to balance future budgets? The trustees also approved a “Library of Things” borrowing policy, a mileage reimbursement increase, and the library’s FY28 action plan.

Trustees President Austin Sarat and Trustees Tamson Ely, Lee Edwards, Nat Larson, Eugene Goffredo, and Farah Ameen took part, along with Library Director Sharon Sharry and Friends president Marian Walker. There was no public comment. The meeting was recorded.

Sarat Puts Friends Agreement on Hold, Eyes Other Funding Options

For several months, trustees and the Friends have been tackling a revised MOU to overhaul library fundraising—weighing whether to place ongoing capital and endowment fundraising permanently under the Friends’ umbrella, drop the traditional 80/20 split of transferred funds, and seat two trustees and the library director on the Friends’ board.

Sarat reported that he recently attended a Friends Development Committee meeting to observe their talks, but surprised colleagues by asking to table the agreement indefinitely. “I would like to ask that we delay any further discussion of the Memorandum of Understanding,” Sarat said. “I am exploring other options for dealing with the funding of the library. And until I have a chance to do that, maybe it would be a little premature to move forward with the Memorandum of Understanding.”

The memorandum would reshape how trustees and Friends share fundraising duties. Larson, who has worked on it, was open but pointed: “if, Austin, you have new ideas and a new approach, I think everyone will be all ears.”

Concerns Over ‘Budget Nimbleness’

Fundraising questions spilled into the Budget and Investment Committee report. Treasurer Lee Edwards reported that the endowment stood at $9,418,948 on October 31, alongside $343,228 in the Woodbury Fund, and said the FY27 budget remains on track.

Sarat worried about the fallout if the board withdraws $3 million to $4 million from the endowment to satisfy its $13.8 million building pledge to the town—a move that would shrink annual investment draws supporting operations. He asked whether Sharry had discussed FY28 budget impacts with Town Manager Paul Bockelman. When Sharry said she had not, Sarat urged immediate talks: “Shouldn’t we, in the next Budget Coordinating Group round, and maybe it’s not too late, begin to talk with the town about what, if any, implications this is gonna have?”

Sarat also worried about how fast a reconstituted fundraising arm could refill a multi-million-dollar endowment hole. Treasurer Larson noted that the joint development group modeled raising $500,000 annually on top of the Annual Fund—an eight-year climb to recover $4 million. Edwards countered that the Capital Campaign averaged roughly $1 million a year over its decade-long run. Even at that pace, Sarat warned, replenishing $4 million would take four years, requiring “some budget nimbleness in the interim.”

Campaign Passes $10 Million

Edwards reported that the library and Friends gave the town an $850,000 check. The capital campaign logged no new pledges in October, but collected $389,403 in pledge payments and $37,204 in new cash gifts. Total pledges and gifts stand near $10.39 million, per the November 1 report. Sarat called that “an astronomical amount of money to have raised.”

Asked how much has now gone to the town, Edwards did not have the figure and promised it next month. The November 1 report lists $6,956,659 paid toward the trustees’ obligation under the MOU, before the $850,000 check.

The annual fund is also running ahead: $27,882 from 97 donors through October 31, versus $16,972 a year earlier. Edwards credited “the quality of the materials that we’re putting out,” while cautioning that she is skeptical of reading much into month-to-month swings.

See related Jones Library Building Project Financial Status, November 2026: More Than $7 Million Still Owed to Town

New Policies Adopted

Library of Things. The loan collection, once mostly hotspots and instruments, now includes items such as a bike repair kit, binoculars, and trekking poles. The items will sit behind the circulation desk, with three-week loans and no renewals. If a borrowed bike repair kit fails, Ely said, “We are not responsible.” Sarat, puzzled by a $10 fine limit, said, “I thought we were beyond the library fine days.” Sharry said some libraries in the CW MARS consortium still charge overdue fines, “believe it or not.”

Source: joneslibrary.org

Mileage. Ely said the new staff reimbursement rate is 76 cents a mile, up from the low 70s. Larson proposed following IRS rates automatically in future years, and Ely amended her motion. Sharry put the budget line at “a few hundred dollars, if that”; Sarat wants the exact figure next meeting.

Action plan. The FY28 plan must reach the Massachusetts Board of Library Commissioners by December 1. Sharry said it may be the last: after reopening, the library will hire a consultant to write a full five-year plan.

AI policy. The Town’s AI use policy, adopted September 21, bars staff from entering sensitive or confidential information into AI tools. It reached the library “for information purposes only.” Ely said, “Unfortunately, they didn’t consult the library, which was too bad.” Sharry said staff were “a little disappointed” and that the town is viewing AI “through a different lens than what the librarians are.” Sarat asked the Personnel, Planning and Policy Committee to take up AI and the library.

Click for more info. Source: joneslibrary.org

Spread the love

Leave a Reply

The Amherst Indy welcomes your comment on this article. Comments must be signed with your real, full name & contact information; and must be factual and civil. See the Indy comment policy for more information.

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.