Jones Library Construction Update
Jones library expansion addition under construction. Photo: amherstma.gov
Report on the Meeting of the Jones Library Building Committee, Nov. 16, 2026
This meeting was held over Zoom and was recorded.
Present
Austin Sarat (Jones Library trustee, chair), Sharon Sharry (library director), Paul Bockelman (town manager), Sean Mangano (town finance director), George Hicks-Richards (library building facilities supervisor), Alex LeFebvre, Christine Gray-Mullen, and George Ryan (town councilor). Staff: Bob Peirent (town special projects manager)
The Jones Library Building Committee (JLBC) meeting on Nov. 16, 2026, was devoted to brief reports on the state of construction.
Construction Update
Exterior work last month included sidewalk, paving, and curb installation, Goshen stone seat wall at the front entry using stone salvaged from the previous garden area, and wooden railing replacement on the eastern side of the building. On the interior, work included the main staircase, drywall, painting, elevator installation, acoustic ceiling tiles, electrical, plumbing, and HVAC work, and the beginning of millwork installation.
Schedule Update
Trey Logie from Colliers (the Owner’s Project Manager) reported no changes to the schedule, with substantial completion expected at the end of March, furnishings and equipment installation by mid-April, and closeout by the end of May. The library’s opening to the public was estimated to be the end of June or early July.
Lights & Construction Hours
Neighbors of the library site raised some concerns about lights left on after construction hours. Site work is supposed to only occur between 7:30 a.m. and 4:30 p.m. but lights were reported being on outside of those hours. Logie acknowledged that the work hours have been exceeded but indicated that the timers on the lights have been reset back to 6 a.m. to 5 p.m.
Interior Design
Some members of the JLBC had inquired about the interior color palette (for tiles, painting, flooring, carpet tiles, etc). These can be viewed in the meeting packet materials.
Invoices/Contingency
A total of $2,233,821.25 in invoices was approved by the committee as follows:
Colliers (Owner’s Project Manager) $ 39,620.73
Fontaine Bros. (General Contractor) $ 2,115,536.10
FAA (Designer) $ 52,261.00
NV5 (Commissioning Agent) $ 5,325.00
Slobody (rent at temporary location) $ 21, 078.42